Tepco Delays Kashiwazaki-Kariwa No. 7 Anti-Terrorism Facility, Pushing Back Reactor Restart
Tepco will extend the completion timeline for the anti-terrorism facility at its Kashiwazaki-Kariwa No. 7 reactor beyond August 2029 due to construction delays.
The turbine floor inside the Unit 7 reactor building during a media tour at Tokyo Electric Power Co.'s (Tepco) Kashiwazaki Kariwa nuclear power station in Kariwa Village, Niigata Prefecture, Japan, on Friday, May 1, 2026. Tepco has started commercial operations at one of its reactors in Japans largest nuclear power plant this month, a crucial development as the Iran war curtails vital energy flows from the Middle East. Photographer: Toru Hanai/Bloomberg Tokyo Electric Power Company Holdings (Tepco) said on 26 November it will review its plan to complete an anti-terrorism facility for the No. 7 reactor at its Kashiwazaki-Kariwa nuclear power plant in Niigata Prefecture by August 2029, after its contractor said construction needs to be extended by more than a year.
The contractor cited factors including labour shortages, Tepco said. The development is expected to further delay the restart of the No. 7 reactor. No revised completion target has been set.
April 2031 Target
Takeyuki Inagaki, manager of the plant, told a regular news conference on Thursday that Tepco aims to complete the facility for the No. 7 reactor by April 2031.
An anti-terrorism facility has also yet to be completed for the plant’s No. 6 reactor, which was restarted in January this year. That reactor will be unable to continue operating unless its facility is finished by April 2031.
Earlier Delays
Japan’s nuclear safety standards, introduced after the March 2011 triple meltdown at Tepco’s tsunami-hit Fukushima No. 1 nuclear power station, require anti-terrorism facilities to be installed within five years of the approval of reactor construction plans.
The initial deadline for the No. 7 reactor had been October 2025. Tepco pushed the facility’s completion back to August 2029 as regulatory reviews for the reactor’s restart took longer than expected, and opted to bring the No. 6 reactor back online ahead of the No. 7 reactor.