Vietnam Pushes Ninh Thuan Nuclear Plants to 2037–2040 in Revised Power Plan
Vietnam’s Ministry of Industry and Trade plans Ninh Thuan 1 to operate in 2037–2038 and Ninh Thuan 2 in 2039–2040, later than the earlier 2030–2035 target.
Vietnam’s Ministry of Industry and Trade plans for the Ninh Thuan 1 nuclear power plant to be operational in 2037–2038 and Ninh Thuan 2 in 2039–2040, later than the 2030–2035 window set in the earlier revision of Power Development Plan VIII.
Quick Skim
The timelines are part of the ministry’s second round of proposed adjustments to Power Development Plan VIII, in which it presented nine power source development scenarios under high demand conditions and proposed scenario KB2A as the main option, Construction Review reports.
Ninh Thuan 1 Set for 2037–2038
Ninh Thuan 1, invested by Vietnam Electricity Group (EVN), has submitted a pre-feasibility study to the Ministry of Finance. The calculations use two generating units of 1,200 MW each, in line with the technology solution of partner Rosatom.
According to the Russian partner and the planning consultancy, the minimum time from feasibility study to plant operation is about 12 years. EVN is still proposing an earlier 2034–2035 timeline if favourable mechanisms and policies are in place.
Ninh Thuan 2 Targeted for 2039–2040
Vietnam National Energy Industry Corporation (Petrovietnam) is conducting a pre-feasibility study for Ninh Thuan 2, which would have two generating units of 1,455 MW each with a South Korean technology partner. The investor estimates operation in 2039–2040 and has proposed an earlier 2035–2036 date, subject to favourable conditions.
Nuclear Capacity and Capital to 2050
The revised Power Development Plan VIII approved in February 2025 had projected both plants operating between 2030 and 2035, with a total capacity of about 4,000–6,400 MW. Under scenario KB2A, nuclear capacity is projected at about 30,771 MW by 2050, with capital requirements for 2026–2050 estimated at around US$187.3 billion.
More Wind, Solar, Storage and LNG Adjustments
Alongside the nuclear changes, the ministry plans to significantly increase wind power, solar power and energy storage, and to adjust the scale of LNG-fired power plants to ensure supply amid the risk of delays in many large power projects.
The ministry also proposes studying special mechanisms for investment, capital mobilisation, human resource development and infrastructure, promptly implementing the projects in Ninh Thuan, and reviewing potential nuclear power sites in northern Vietnam to provide a stable, long-term base power source.