KT Cloud Partners With Keppel to Build 110 MW AI Data Centre Cluster in Ansan
KT Cloud will combine the 50 MW Ansan 1 and 60 MW Ansan 2 AI data centres into a 110 MW campus, with Ansan 2 due to open in 2030.
KT Cloud will build a 110 MW artificial intelligence data centre (AIDC) cluster in Ansan, Gyeonggi Province, as a partner in Singapore-based asset manager Keppel’s first data centre development project in South Korea, The Elec reported.
Keppel Partnership
KT Cloud announced on 26 November that it would participate as a partner in the Keppel project.
The company plans to integrate operations of the 50 MW Ansan 1 AIDC, currently under construction, with the new 60 MW Ansan 2 AIDC to form a 110 MW campus.
Ansan 2 Facility Design
Ansan 2 AIDC will have a total power intake capacity of 60 MW and a gross floor area of 52,622 square metres (about 15,918 pyeong), with two underground and eight aboveground floors.
All floors will feature infrastructure supporting liquid cooling to manage heat generated by high-performance graphics processing unit (GPU) servers and meet demand for high-density AI servers.
Timeline and KT Group Expansion
Construction of Ansan 2 AIDC begins in November, with operations scheduled to start in 2030. The facility is located about 2.5 kilometres from Ansan 1 AIDC.
The project is part of KT Group’s strategy to expand its AIDC capacity. The group aims to provide more than 1 GW of AIDC capacity by 2031, following detailed plans for key locations including Gunsan and Cheongna.