Yongin Completes Substation and Water Test for SK Hynix’s KRW 31 Trillion First Fab
SK hynix will open the first cleanroom of its first-phase Yongin fab in February 2027, three months ahead of plan, as the city reports a finished substation and a successful water test.
SK hynix will open the first cleanroom of its KRW 31 trillion first-phase Yongin fab in February 2027, three months earlier than planned, as Yongin City reports that the site’s substation and transmission line are built and an industrial water test discharge has succeeded.
Quick Skim
First Cleanroom Moved Up From May to February 2027
According to The Asia Business Daily, the SK hynix Yongin Semiconductor Cluster covers 4.15 million square metres in Wonsam-myeon, Cheoin-gu, Gyeonggi Province, with more than 20,000 workers on site each day. With demand surging for high-performance memory including high-bandwidth memory (HBM), SK hynix moved the first cleanroom opening from May 2027 to February.
The KRW 9.4 trillion initial investment approved in July 2024, combined with an additional KRW 21.6 trillion approved in February 2026, brings total investment in the first-phase fab and its infrastructure to KRW 31 trillion. The remaining five cleanrooms in the first-phase fab are to come into operation sequentially by the end of 2030.
Substation, Transmission Line and Water Test Completed
Yongin Mayor Lee Sangil worked with the central government and relevant agencies to coordinate water and power supply to the Wonsam General Industrial Complex. A test discharge from the industrial water supply facility was completed in June 2026, and construction of the Dongyongin Substation and the Shinanseong-Dongyongin transmission line is complete.
Plans are also under way to develop sites for about 50 materials, parts and equipment companies, along with a “minifab” for testing and demonstration. Partner companies would be able to test materials and equipment under conditions similar to actual semiconductor production.
City Plans Traffic Measures, a Semiconductor School and a Rail Fund
To avoid a repeat of the congestion seen early in Wonsam construction, the city plans traffic measures before work on the Idong-Namsa National Industrial Complex picks up pace. These include detour routes for construction vehicles, restrictions on their operation at rush hour, and a hub parking lot of approximately 60,000 pyeong and temporary accommodations.
Yongin Semiconductor High School will open in March 2027 with a capacity of 134 students and recorded 4.84 applicants per place in its first general admissions round. The city plans to pursue its conversion into a Meister high school in 2028.
On 13 November, Lee met Minister of Land, Infrastructure and Transport Hong Jiseon and asked him to include the South Gyeonggi Metropolitan Railway, the Gyeonggang Line extension and the South Gyeonggi East-West Transversal Line (Semiconductor Line) in the Fifth National Railway Network Construction Plan. He proposed a city-funded rail fund of KRW 500 billion to KRW 1 trillion by 2030, financed from part of the tax revenue expected from semiconductor investment.
Samsung Fabs and Giheung Campus Complete the Megacluster
The Advanced System Semiconductor National Industrial Complex, where Samsung Electronics will build six fabs, has begun site preparation. With the Giheung Campus, which will house a next-generation research complex, the region will form what the report calls the world’s largest semiconductor megacluster, spanning memory in Wonsam, system semiconductors in Idong and Namsa, and research and development in Giheung.
Lee said the city will “provide complete support for infrastructure, transportation, and living conditions so that nothing stands in the way of companies securing an overwhelming technological lead”.