PLN Batam Energises 150 kV Tanjung Sauh Substation and Upgrades Sagulung Plant
PLN Batam put the 150 kV Tanjung Sauh substation into operation on 9 November and implemented Free Governor and Black Start at the 60 MW Sagulung gas-engine plant.
PT PLN Batam is strengthening the Batam-Bintan power system through the 150 kV Tanjung Sauh substation, energised on 9 November 2026, and ‘Free Governor’ and ‘Black Start’ systems at the 60 MW Max Power Sagulung gas-engine plant.
Tanjung Sauh Substation Energised
PLN Batam Corporate Secretary Mulnawarman said both developments are part of efforts to keep improving the quality and reliability of electricity service through innovation and continuous system refinement. He said the successful operation of the Tanjung Sauh substation on 9 November 2026 was an important milestone for the Batam-Bintan transmission infrastructure.
The company said it improves the connectivity and flexibility of the grid and prepares the system to support the development of energy supply and growing power demand in both areas.
Sagulung Plant Gets Black Start and Free Governor
PLN Batam and Max Power also raised operational readiness at the Max Power Sagulung gas-engine plant (PLTMG) by implementing Free Governor and Black Start. Black Start is a battery-supported system for starting the plant’s engines, allowing faster restoration of the power system, particularly during system disturbances.
Free Governor helps maintain frequency stability and the power balance of the system.
Photo: ANTARA