Rio Tinto Signs 50 MW Electricity Deal With Contact Energy to Restart Line 4 at Tiwai Point
Rio Tinto will restart additional smelting capacity at Tiwai Point in New Zealand after signing a 50 MW electricity agreement with Contact Energy.
Rio Tinto will restart additional smelting capacity at its Tiwai Point aluminium smelter in New Zealand after signing a three-and-a-half-year, 50 MW electricity agreement with Contact Energy.
Quick Skim
The agreement will enable Line 4 to return to operation backed by predominantly renewable energy. The restart is scheduled for October 2027, with full production expected by December 2027.
Line 4 Restart Adds Approximately 30,000 Tonnes of Annual Output
Once fully operational, the restart is expected to add approximately 30,000 tonnes of aluminium a year, restoring the smelter to approximately 360,000 tonnes per annum. This adds approximately 3% smelting capacity across Rio Tinto’s Australia and New Zealand operations.
Based on current global spot aluminium prices, the additional output could generate around NZ$100 million in annual export revenue for New Zealand, according to Rio Tinto.
Contract Backed by Renewable Energy, With Winter Supply Cut to 25 MW
The agreement with Contact Energy will enable Rio Tinto to bring Line 4 back into operation backed by predominantly renewable energy. The contract is structured to reduce supply to 25 MW over winter months to ensure there is no impact on New Zealand’s broader energy security over that period.
The bridging agreement builds on a Letter of Intent between Contact Energy and Rio Tinto announced earlier this year. The parties are continuing to develop a longer-term power purchase agreement that could see Line 4 operate for at least the next two decades.
Line 4 Has Been Idle Since April 2020
Line 4 has been idle since April 2020 as a result of the impact of the COVID-19 pandemic on global industrial markets, followed by a period of uncertainty about the long-term future of the smelter. Since then, Rio Tinto has secured long-term electricity supply arrangements into the next decades.
Rio Tinto Aluminium Pacific Operations Managing Director Armando Torres said: “The restart of Line 4 will increase aluminium production at a time when demand for high quality, low carbon aluminium has never been higher.”
Rio Tinto Calls Early Restart Good News for Southland
Rio Tinto New Zealand Aluminium Smelters General Manager Michelle Henderson said: “This agreement enables an early restart of Line 4 while the parties continue to develop a longer-term power purchase agreement that could see Line 4 operate for the next two decades at least. This is great news for the Southland and wider New Zealand economies.”
Both parties acknowledged the constructive engagement undertaken since the announcement of the earlier Letter of Intent, according to Rio Tinto.
Photo: Evil Monkey/Wikimedia Commons, CC BY 2.5