EnergyCo Appoints Transgrid to Deliver New 500 kV Hunter Transmission Line
EnergyCo has awarded Transgrid the contract to build a 110 km 500 kV transmission line in New South Wales, enhancing capacity for renewable energy integration.
The New South Wales government, through its energy agency EnergyCo, has contracted Transgrid to deliver the Hunter Transmission Project (HTP), a transmission upgrade featuring a new 110-kilometre 500 kV line designed to connect key renewable energy zones and support coal generation retirement.
Quick Skim
Project Comprises New Transmission Line and Substation Upgrades
The HTP involves constructing a 500 kV double-circuit transmission line between the Bayswater area in the Upper Hunter and Olney in the Lower Hunter regions. It will link existing 500 kV infrastructure operated by Transgrid. The work includes new switching stations at Bayswater South and Olney State Forest, alongside upgrades to the Bayswater and Eraring substations.
EnergyCo describes the project as a critical grid element that will connect the New England and Central-West Orana renewable energy zones (REZs) to demand centres in Hunter, Sydney, and Illawarra.
Project Capacity and Economic Impact
The Hunter Transmission Project is expected to unlock up to 5 GW of additional electricity transfer capacity along this key corridor. EnergyCo Chief Executive Officer Hannah McCaughey said the infrastructure will enable access to lower-cost renewable energy as coal-fired power stations progressively retire.
The construction phase is forecast to generate about 900 jobs and provide economic benefits to local businesses, with approximately 90% of the corridor following government and industry-owned land to reduce impact on residential and environmental areas.
Downer Secures Contract for Transmission Line Works
Downer EDI Limited was awarded an approximately A$1.1 billion contract by EnergyCo to deliver transmission line works for the project, in partnership with Transgrid. The contract covers a three-year construction period and the delivery of about 110 kilometres of new double-circuit 500 kV transmission lines and lattice steel structures between the Bayswater South and Olney switching stations. Planning, design and procurement activities are expected to begin in December 2026, with on-site mobilisation scheduled for 2027, subject to final approvals.
Downer CEO Peter Tompkins said the firm engaged in a multi-year process addressing design and risk management before contract award, and the agreement includes lump-sum and variable elements to accommodate project uncertainties.
Transgrid to Lead Delivery and Long-Term Operations
Transgrid Chief Executive Brett Redman stated the company will oversee detailed design, engineering, and construction management with a focus on safety and efficiency. Once complete, Transgrid will manage the operation and maintenance of the new infrastructure over the long term.
Construction is scheduled to begin in 2027, aiming for full commissioning by late 2029.
EnergyCo will continue in its role as infrastructure planner and overseer throughout the delivery process, maintaining oversight of design and construction activities performed by Transgrid, Downer, and UGL, the latter responsible for substation works.
Photo: EnergyCo