Ho Chi Minh City Targets Late-November Opening of 17 km Ring Road 3 Elevated Section
Construction progresses on key transport projects in eastern Ho Chi Minh City, with an elevated expressway section nearing completion and interchanges scheduled for 2026–27.
Ho Chi Minh City is targeting late November 2026 to open a 17-kilometre elevated section of Ring Road 3 to traffic, as crews work around the clock on several eastern transport projects.
Quick Skim
Thousands of engineers, workers, and heavy machinery operate at multiple sites around the clock, advancing elevated roadways, interchanges, and expressway expansions.
Ring Road 3 Elevated Section Nears Traffic Opening
The Tan Van interchange and surrounding sites along the 58.54-kilometre Ring Road 3 corridor demonstrate extensive construction activity. The elevated expressway segment stretching about 17 kilometres from the Tan Van interchange toward the Ho Chi Minh City – Long Thanh – Dau Giay Expressway interchange is under construction.
Engineering teams prioritise installation of cantilever structures, bridge spans, and elevated deck surfaces, supported by strict quality, technical, and workplace safety controls. Asphalt paving, guardrail mounting, lighting system installation, and lane marking are well advanced across packages XL1 to XL5.
Nguyen Thanh Tung, construction supervisor for the Tan Van interchange overpass branch, highlighted continuous operations and proactive problem-solving on site to adhere to schedules aiming for the section’s opening to traffic by late November 2026, aligning with Long Thanh International Airport’s operational timetable.
Progress on An Phu and My Thuy Interchange Projects
The An Phu interchange in Binh Trung Ward features a three-level design with two underpasses (HC1-01 and HC1-02) and four overpass branches (N1–N4). It has attracted a capital investment of approximately VND3,408 billion (US$132.2 million). Following recent openings of some bridge branches, efforts continue on remaining structures and auxiliary infrastructure.
The project aims to complete critical bridge branches N1.1 and N1.3 by late December 2026, while branch N1.2 and Luong Dinh Cua Street expansion target completion by late April 2027. The entire interchange is planned for final delivery by 30 April 2027.
The My Thuy interchange, with an investment of about VND3,622 billion, has reached approximately 85% construction volume, targeting completion in the first quarter of 2027. Around 400 workers and 112 machinery units support progress at both interchanges.
Expressway Expansion, Scale and Remaining Work
Construction on the Ho Chi Minh City – Long Thanh – Dau Giay Expressway expansion segment through Ho Chi Minh City and the adjacent My Thuy interchange advances with multiple crews conducting concrete, structural, and technical infrastructure works simultaneously. At the Phu Huu to Pham Van Dong Ring Road 2 gap-section, roughly 20 construction fronts operate two shifts daily, including three continuous shifts for piling and soil stabilisation.
The Ring Road 3 project mobilises 194 construction fronts, over 3,000 engineers and workers, and around 700 equipment units. The Ho Chi Minh City Management Board for Investment and Construction of Traffic Works oversees two sub-project components: Component Project 1 has 10 main packages, with more than 85% of contract volume completed, and Component Project 5 has reached 80%.
Beyond primary road and bridge construction, contractors are focusing on soft soil treatment, surcharge removal on stabilised land, crushed stone aggregate base construction, and asphalt paving. Ancillary infrastructure such as an intelligent transportation system, operations centre, and vehicle weigh stations are scheduled for completion in early 2027.
Photo: SGGP