Thai Cabinet Backs Direct EGAT Power Sales to Data Centres of 200 MW or More
Thailand’s Cabinet endorses a draft decree allowing data centres with 200 MW-plus demand to buy power directly from EGAT’s high-voltage network.
smacap_Bright Thailand’s Cabinet has approved a draft royal decree that would allow data centres requiring at least 200 MW of electricity per project to buy power directly from the Electricity Generating Authority of Thailand (EGAT).
Quick Skim
According to a Government House source, the Cabinet endorsed the Ministry of Energy’s proposal to amend Section 3 of the 1989 Royal Decree on Electricity Users. The amendment would create a new category of electricity consumers, allowing qualifying data centres to become direct EGAT customers connected to its high-voltage transmission network.
Protecting grid stability as AI demand grows
The proposal responds to the rapid growth of artificial intelligence (AI) services and large-scale data centres, which require substantial, continuous electricity supplies. Projects with electricity demand of 200 MW or more could place significant pressure on the national network, potentially affecting grid stability, reliability and the balance between supply and demand.
Connecting these facilities directly to EGAT’s high-voltage transmission system, rather than through medium- and low-voltage distribution networks, is intended to minimise disruption to smaller consumers and avoid unnecessary investment in duplicate infrastructure.
Direct connections could also help operators manage rapid fluctuations in demand, known as dynamic load swings, while supporting the N-1 reliability standard and 2N power redundancy arrangements. Improved supply reliability could reduce operators’ need to invest in duplicate backup power systems, lowering project costs.
Three benefits outlined by the Energy Ministry
According to the Government House source, the Energy Ministry outlined three areas in which the amendment would benefit the country. Managing large, continuous loads through the transmission network would improve overall grid reliability, reduce the risk of voltage fluctuations and power outages, and make better use of existing generation capacity.
Reliable power access would encourage foreign investment in high-value digital infrastructure, create highly skilled jobs and promote the transfer of advanced technologies. Avoiding duplicate distribution infrastructure and making more efficient use of existing power purchase agreements could also help contain electricity costs over time, while protecting households and smaller businesses from disruptions caused by large electricity loads.
Managing power purchase agreements
The ministry expects the measure to improve EGAT’s management of electricity generation under existing and future power purchase agreements. Steady, high-volume consumption from data centres could help optimise generation and make better use of capacity already subject to contractual availability payment obligations.
Photo: Sry85/Wikimedia Commons, CC BY-SA 4.0