The 19 data centres in Johor consume 21.277 million litres per day of treated water, Mohamad Fazli Mohamad Salleh told the state assembly.
The 19 data centres operating in Johor consume 21.277 million litres per day (MLD) of treated water, 1.05% of the state’s total treated water production, said State Public Works, Transport, Infrastructure and Communications Committee chairman Mohamad Fazli Mohamad Salleh.
Quick Skim
Approved Volume Well Below Initial Request
Mohamad Fazli, who is also the Bukit Pasir assemblyman, was speaking at the Johor state legislative assembly in Kota Iskandar, as reported by Malay Mail, The Star and AsiaOne, in response to questions from Baharudin Mohamed Taib (BN-Permas), Pandak Ahmad (BN-Kota Iskandar) and R. Kumaran (BN-Bukit Batu).
The data centres initially requested 73.088 MLD of water, but 21.277 MLD was approved, which is 3.35% of the industrial sector’s total water consumption. Johor produces an average of 2,034 MLD of treated water, of which 904 MLD is used for domestic purposes and 635 MLD by industries.
Water-Free Cooling and Alternative Sources
Nine of the 19 operational data centres use efficient cooling systems capable of operating with zero water consumption.
Operators with high water requirements have been asked to use alternative water sources via Johor Special Water (JSW), including treated wastewater from sewage treatment plants.
“Despite the data centres’ low water usage, making up only a small fraction of the state’s total treated water production, the state government will ensure that it does not compromise the needs of domestic consumers in the future,” he said.
Coordination Committee and Dam Levels
Johor was the first state to establish the Johor Data Centre Development Coordination Committee (JPPPDNJ), in 2024. Through the committee, water and electricity supply requirements are assessed with the Johor Water Regulatory Body (BAKAJ), Ranhill SAJ (RSAJ), JSW and Tenaga Nasional Berhad (TNB).
The 19 data centres receive their supply from the Semangar and Sungai Johor water treatment plants, both of which draw raw water from Sungai Johor.
Mohamad Fazli attributed falling water levels at six dams to the prolonged drought and the El Niño phenomenon, which is expected to have its peak impact through March 2027. The six dams under monitoring are Machap, Lebam, Gunung Pulai 2, Pontian Kechil, Upper Layang and Lower Layang. The Machap and Lebam dams do not supply water to any data centres.
Photo: Reuters file/AsiaOne. A data centre in Gelang Patah, one of 19 operating in Johor.