SCGC and Denka Open US$400 Million Acetylene Black Plant in Rayong
SCGC and Denka inaugurated the DSAM plant in Rayong with 11,000 tonnes annual capacity to supply acetylene black for EV batteries and renewable energy infrastructure.
H.E. Otaka Masato, Ambassador of Japan to Thailand, and Salareewan Thapthawee, Deputy Governor of Rayong Province, attended the official opening of a SCGC–Denka joint-venture acetylene black plant at RIL Industrial Estate in Map Ta Phut, Rayong.
Quick Skim
Quick Skim
-
Japanese Ambassador and Rayong Deputy Governor Attend Opening
-
Joint Venture Plant Has 11,000-Tonne Annual Capacity
-
US$400 Million Figure Comes From Denka’s 2023 Investment Notice
-
Commercial Operations Scheduled for January 2027
Japanese Ambassador and Rayong Deputy Governor Attend Official Opening
SCG Chemicals Public Company Limited, or SCGC, and Denka Company Limited of Japan officially opened the Denka SCGC Advanced Materials plant, or DSAM, at RIL Industrial Estate in Map Ta Phut, Rayong Province. Denka said the grand opening ceremony was held on 16 November 2026. SCGC dated its announcement 18 November 2026.
The ceremony was co-presided over by Sakchai Patiparnpreechawut, CEO and President of SCGC, and Ikuo Ishida, President and CEO of Denka. SCGC said the event was also attended by H.E. Mr. Otaka Masato, Ambassador of Japan to Thailand, Ms. Salareewan Thapthawee, Deputy Governor of Rayong Province, and Thammasak Sethaudom, President and CEO of SCG, together with representatives from government agencies, business partners and executives from both companies.
Plant Will Produce Acetylene Black for Batteries and Power Cables
DSAM is a joint venture between SCGC and Denka, established to manufacture and distribute high-performance acetylene black, including Denka Black. Denka said the Denka Group holds 60% of the venture and SCGC holds 40%.
According to SCGC, the material is highly pure, with high electrical conductivity, and is produced using Denka’s proprietary thermal decomposition technology. The companies said the product is used in lithium-ion batteries for electric vehicles and energy storage systems, and in high-voltage power transmission cables for renewable energy infrastructure.
The plant has an initial production capacity of approximately 11,000 tonnes per year.
US$400 Million Investment Set in Denka’s 2023 Notice
Denka’s 10 October 2023 investment notice set the amount invested in the plant at US$400 million. In its 17 November 2026 notice, Denka said construction was completed on 31 October 2026.
Denka said commercial operations are scheduled to start in January 2027.