President Lee Visits SK’s Ulsan AI Data Centre Construction Site
South Korean President Lee Jae Myung visited an SK-operated AI data centre construction site in Ulsan on 21 November to check progress of government-led “mega projects”.
South Korean President Lee Jae Myung on Saturday visited an AI data centre construction site operated by SK in Ulsan, some 310 km southeast of Seoul, a day after concluding a four-day trip to the Philippines and China.
Mega Projects Progress Check
The 21 November visit checked progress of government-led “mega projects” to turn three regional areas — Chungcheong, Honam and Yeongnam — into hubs for AI data centres, physical AI and advanced semiconductors, Yonhap News Agency reported.
“AI data centers are a major source of demand for semiconductors and key infrastructure behind physical AI, such as robots and autonomous vehicles,” Lee said.
“I expect the successful progress of the AI data center project in Ulsan will serve as a catalyst for additional investments from global AI companies,” he added.
Support for Construction Workers
Lee said the government plans to provide support to resolve a shortage of construction workers for such advanced facilities.
“When the world is under a heated race, speed is crucial,” he said.
Lee was accompanied by SK Telecom CEO Jung Jai-hun and Science Minister Bae Kyung-hoon.
Ulsan Project Details
SK Group is developing the Ulsan data centre jointly with Amazon Web Services (AWS), Reuters and CNA reported. The estimated cost is 7 trillion won (US$5.2 billion) until 2029, according to South Korea’s science ministry last year, and operations are scheduled to begin in the second half of 2027.
SK Group Chairman Chey Tae-won said in September that the capacity under construction was an initial 103 MW by 2029, with plans to expand by nearly 900 MW. About 900 people were working at the site.
Photo: Yonhap