Hanoi and Giap Bat Railway Operations Conditionally Approved for Transfer to Phu Xuyen
The Ministry of Construction agreed in principle to relocate Hanoi and Giap Bat railway operations to Phu Xuyen, pending technical and operational plan completion.
The Ministry of Construction has conditionally agreed to move all passenger operations at Hanoi Station and freight operations at Giap Bat Station to Phu Xuyen Station, freeing land for Hanoi’s National Highway 1A Spatial Axis Project.
Quick Skim
Conditional Agreement on Railway Operation Transfer
The Ministry of Construction has responded to a proposal from the Hanoi People’s Committee to temporarily move railway operations to Phu Xuyen Station. The ministry agreed with the principle of the transfer but emphasised that the plan requires further detailed study, particularly concerning technical feasibility, train operation organisation, and ensuring uninterrupted rail transport.
The overarching objective is to maintain train safety, meet passenger and freight transport needs, and avoid disruption to the national railway network. The ministry also emphasised the need to minimise impacts on the Vietnam National Railway Corporation’s business and local residents.
Project Timelines and Infrastructure Upgrades
To facilitate land clearance, the ministry proposed that the Government direct the Hanoi People’s Committee to accelerate two related railway projects. The upgrade of the existing Hanoi–Ho Chi Minh City line from Phu Xuyen to Ngoc Hoi station, including a new Thuong Tin station and a national railway transport operations centre, must be completed before 31 March 2027.
The Eastern Ring Road railway project covering the Ngoc Hoi to Kim Son section is scheduled for completion by December 2028.
The ministry also proposed that the Government direct the Hanoi People’s Committee to instruct relevant units to finalise plans to renovate and upgrade Phu Xuyen Station and build new auxiliary facilities, so it has the scale, technical conditions and train operation capacity to absorb all passenger and freight services now handled at Hanoi and Giap Bat stations.
The ministry said the railway section from Phu Xuyen to the existing Hanoi Station can only be handed over to the Hanoi People’s Committee after the temporary station is built and trial-operated to ensure safety and meet transport needs.
Collaboration and Investment by Vingroup
Vingroup Corporation has proposed self-financing 100% of the construction of the temporary station and auxiliary facilities, without using state budget funds. Under the plan, it would coordinate with specialised units of the Ministry of Construction, the Vietnam Railway Authority and the Vietnam National Railway Corporation to review technical conditions, train operation plans and capacity at the temporary station.
Vingroup also proposed advancing land clearance funds to the Phu Xuyen Commune People’s Committee, to be reimbursed if the cleared land falls within the urban development area under the approved transit-oriented development (TOD) model and after Phu Xuyen ceases to serve as a temporary station.
To maintain passenger convenience during the relocation, Vingroup has proposed a free 24/7 bus shuttle service between Hanoi and Phu Xuyen Stations. For freight movements, options include transshipment between Phu Xuyen and Yen Vien Stations or alternative arrangements to prevent congestion and maintain supply chain continuity.
Vingroup proposed keeping the existing railway transport operations centre at Hanoi Station in place during the temporary operation phase, with its relocation to Ngoc Hoi to be studied after the Ngoc Hoi National Railway Station Complex is completed.
Land Clearance and Project Delivery Targets
The National Highway 1A Spatial Axis Project was assigned by the Hanoi People’s Committee to Vingroup under a public-private partnership Build-Transfer (BT) contract, with a target completion of July 2027. According to the Hanoi People’s Committee, land clearance has reached 98.6 of the 262.15 hectares required, or 37.6%.
The Hanoi People’s Committee granted an emergency construction order for the Ngoc Hoi to Phu Xuyen national railway section at the end of August 2026, requiring completion by March 2027.