Medco Completes Sambar-6 Well in Corridor Block With 35 MMSCFD Test Rate
Medco E&P Grissik has completed the Sambar-6 development well in the Corridor Work Area, with a preliminary test rate of 35 MMSCFD, SKK Migas said.
Medco E&P Grissik Ltd. (MEPG) has completed drilling of the Sambar-6 development well in the Sambar Field, Corridor Work Area, with a preliminary test rate of 35 million standard cubic feet per day (MMSCFD) of gas.
Djoko Siswanto, Head of SKK Migas, Indonesia’s Special Task Force for Upstream Oil and Gas Business Activities (Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Migas), said the result met the target set in the 2026 Work Program & Budget (WP&B). He said the well was finished ahead of the programme schedule, according to Dunia Energi.
Drilling Finished 15 Days Ahead of Plan
Sambar-6 was spudded on 7 September 2026 using the EPI AR-09 rig, which has 1,500 HP capacity, targeting the Lower Talang Akar Formation (LTAF). Drilling was completed on 27 September 2026 at a final depth of 2,042 metres measured depth (mMD).
Djoko said drilling took 22 days, 15 days faster than the 37-day programme.
Test Result and Cost
Rigless well testing began on 22 November 2026. The preliminary test reached 35 MMSCFD, flowing naturally at open flow from the LTAF reservoir, in line with the 2026 WP&B target.
Preliminary estimated cost came to US$12,251,894, or 64.29% of the Authorization for Expenditure (AFE) of US$19,056,226.