Vietnam Electricity (EVN), the state-owned national power utility, has introduced new technical requirements and acceptance procedures for rooftop solar systems that export surplus electricity to the grid, under Decision No. 1382/QĐ-EVN issued on 18 November.
Quick Skim
New Technical Requirements for Rooftop Solar Installations
Issued as Decision No. 1382/QĐ-EVN, the new rules replace the earlier Decision No. 378/QĐ-EVN. They set technical specifications and a process for testing and accepting rooftop solar installations connected to EVN’s monitoring, data-collection and control systems. They cover systems designed for self-consumption that export surplus electricity to the grid.
Under the new framework, systems must transmit operational data, including inverter output, to EVN’s monitoring systems at intervals no longer than five minutes. Furthermore, installations are required to support remote commands to curtail exported electricity and automatically adjust inverter output to reflect power limitation instructions from EVN.
Acceptance Testing Procedures and Responsibilities
The acceptance procedure involves several stages: documentation review, on-site inspections, communication protocol testing, and verification of monitoring and control functionalities. Utilities are tasked with testing whether systems can reduce export output on command and assessing performance under communication failures or faults before final acceptance.
System owners are responsible for installing compatible monitoring, metering, and communication devices, submitting technical documentation, and coordinating with EVN during testing phases. Conversely, EVN and affiliated electricity companies provide connectivity and communication configurations, verify cybersecurity measures, evaluate monitoring system functionality, and conduct the final acceptance tests.
Context of Vietnam’s Rooftop Solar Growth
The decision comes as Vietnam looks to accelerate rooftop solar deployment. The government ordered provinces to speed up rooftop solar support policies in September and later called on provincial and municipal authorities to introduce them by the end of the year.
A publication by the Ministry of Industry and Trade earlier in September outlined a shift towards integrating rooftop solar with behind-the-meter battery energy storage and electric vehicles, enhancing grid flexibility beyond traditional time-of-use tariffs.
Vietnam’s solar capacity surpassed 19 GW by the end of 2025, with around 586 MW added that year. EVN data show the country had more than 11.45 GW of rooftop solar capacity across 134,410 installations as of the end of August 2026.