PGN Advances Six Energy Infrastructure Projects to Expand Gas Supply and Services
PGN is advancing six infrastructure initiatives in 2026, backed by US$353 million in capital expenditure, including LNG storage, regasification, biomethane injection and pipeline projects.
PT Perusahaan Gas Negara (Persero) Tbk (PGN) is strengthening its infrastructure and expanding the natural gas market through six strategic initiatives scheduled for implementation throughout 2026, ANTARA reported.
Quick Skim
Six Initiatives and US$353 Million in Capex
According to a statement received in Jakarta on Friday, the six initiatives are the construction of the Teluk Lamong LNG facility, the New West Java Regasification project, the development of household gas networks (jargas), the Pagardewa biomethane injection facility, the customer attachment program and the construction of the Cikampek-Plumpang oil pipeline.
In 2026, PGN allocated US$353 million in capital expenditure (capex), with most of the funds directed toward downstream business development and supporting infrastructure. As of September 2026, capex realisation had reached US$151 million.
“These strategic projects are part of PGN’s efforts to strengthen infrastructure reliability and expand natural gas utilization,” PGN Corporate Secretary Fajriyah Usman said.
LNG Storage and Regasification Projects
PGN is preparing to construct a flat-bottom LNG storage tank facility in Teluk Lamong, East Java, with a planned capacity of 30 BBTUD. As of September 2026, the project’s physical progress had reached 0.9%, with commissioning targeted for the second quarter of 2028.
The New West Java Regasification project is designed to support a planned increase in regasification capacity of up to 500 MMSCFD. It includes the construction of an approximately 28 km interconnection pipeline linking Jakarta Bay and Muara Bekasi, and is targeted to commence operations in the third quarter of 2028.
Household Gas, Biomethane and Pipeline Work
In 2026, the jargas program targets 50,000 potential household connections across seven provinces and 11 cities. As of September 2026, PGN had developed 280 km of pipeline networks, providing potential connections for 36,401 households.
PGN is constructing a biomethane injection facility in Pagardewa, South Sumatra, with a planned capacity of 1.2 BBTUD. Physical construction progress had reached 76.6% as of September 2026, with commissioning targeted for the first quarter of 2027.
The customer attachment program is expanding natural gas distribution networks across 10 provinces and 17 cities. With an investment allocation of US$21.74 million in 2026, it is expected to generate additional potential gas sales volume of 30.57 BBTUD. As of September 2026, capex realisation for the program had reached US$11.29 million.
Through its subsidiary PT Pertamina Gas (Pertagas), PGN is also constructing the 96 km Cikampek-Plumpang oil pipeline in West Java, with a planned capacity of 79,800 barrels of oil per day (BOPD), intended to improve fuel distribution reliability across Greater Jakarta. As of September 2026, physical construction progress had reached 64.6%, with commissioning targeted for the third quarter of 2027.