Vietnam awarded an international consortium a $399 million contract to conduct technical surveys and design for its 1,541 km high-speed rail linking Hanoi and Ho Chi Minh City.
Vietnam’s Ministry of Construction has appointed an international consortium to undertake a $399 million consultancy contract for the design and feasibility study of the North-South high-speed rail project connecting Hanoi and Ho Chi Minh City.
Quick Skim
Consortium Awarded 30-Month Consultancy for Project Preparation
The Thang Long Project Management Board, under the Ministry of Construction, selected an eight-company consortium to deliver consultancy package TV-02. The group is led by French engineering consultancy SYSTRA and includes South Korean firms Sambo Engineering, Yooshin Engineering Corporation, and Korea National Railway (KNR), alongside four Vietnamese partners.
The consortium’s bid was approximately VND10.24 trillion, equivalent to $399 million, within a total estimated contract value of around $420 million. The consultancy contract will last 30 months after commencement.
Services include technical surveys, preparing a feasibility study, developing front-end engineering design (FEED), and producing bidding documents for the subsequent construction phases of the project.
Feasibility and Engineering Design Define Technical and Financial Framework
The consultancy will assess the optimal alignment of the approximately 1,541-kilometre railway corridor from Ngoc Hoi Station in Hanoi to Thu Thiem Station in Ho Chi Minh City. The scope covers key infrastructure requirements such as stations, bridges and tunnels.
The FEED will examine various railway technologies and investment models to establish the project’s technical and economic viability. Results will guide government decisions on financing and the structure of investment prior to awarding construction contracts.
Project Specifications and Regional Integration Challenges
The proposed high-speed rail will use double standard-gauge tracks measuring 1,435 millimetres, designed for service speeds up to 350 kilometres per hour. The new line is intended to reduce travel time between Hanoi and Ho Chi Minh City from about 30 hours to roughly five hours, improving passenger mobility across 15 provinces and centrally-governed cities.
Land acquisition and coordination across multiple administrative jurisdictions present significant challenges. The Ministry of Construction has instructed the consortium to minimise disruption to local communities and ensure alignment with regional development plans. Vietnam postponed the construction timeline by one year, pushing the expected start towards the end of 2027, with land clearance anticipated to complete by the fourth quarter of 2028.
Consultancy Prepares Procurement Documentation but Excludes Construction
The $399 million contract covers preparatory work including investment planning, engineering assessment and procurement preparation but does not include construction. The consultancy will develop procurement documents to establish technical specifications and facilitate clearer contractor selection for future construction contracts.