Squadron Energy Proposes A$1.5 Billion, 8,000 MWh Cullen Bullen Battery Near Lithgow
Andrew Forrest's Squadron Energy has filed a scoping report for a 1,000 MW battery with up to eight hours of storage near Lithgow, west of Sydney.
Andrew Forrest’s Squadron Energy has filed a scoping report for the A$1.5 billion Cullen Bullen battery near Lithgow, west of Sydney, a 1,000 MW facility with up to 8 hours of storage that would be the biggest battery in Australia.
The proposal, for up to 8,000 MWh of storage, has been lodged with the state’s planning authority, and Squadron hopes to connect it to an existing 500 kV transmission line, RenewEconomy reported.
Site and Timing
The battery would be located around 25 km north of Lithgow and 130 km north-west of Sydney, on around 660 hectares of land already cleared for grazing. Squadron hopes to begin construction in 2030.
It would sit next to the Cullen Valley coal mine and around 1.2 km from Alinta Energy’s proposed 500 MW Ben Bullen wind project.
A Region Moving Away From Coal
The area is already slated to host the Sunny Corner and Mount Lambie wind projects, the Mt Piper, Wallerawang, Pinecrest, Great Western and Ivanhoe batteries, and the Mt Lyell pumped hydro storage project.
The Wallerawang coal-fired power station has already been shut, and the Mt Piper coal generator is due to close in the next decade.
Grid Role
Squadron says the battery would provide voltage control and back-up power for the grid. “The objective … is to provide storage and firming for the electricity grid,” the scoping report says.
According to the report, the battery would help manage grid stability and inertia by balancing the peaks and troughs of renewable energy generation, helping to integrate a greater share of renewable energy generation into the National Electricity Market.
Community Benefit Sharing
“We want to hear from local residents and businesses as we develop this proposal, understand what matters to them and identify opportunities for the project to benefit the wider community,” project director Sean Cross said.
Squadron says it is committed to a voluntary planning agreement with Lithgow City Council, contributing to a total benefit-sharing funding rate of A$150 per MWh per annum under the state’s Benefit-Sharing Guidelines, with a proportion intended to go directly to Cullen Bullen and surrounding communities.
Photo: Squadron Energy