PTSC Offshore Services Completes Block B Turret Mooring System for Offshore Gas Project
PTSC Offshore Services has fabricated, pre-commissioned and handed over the Block B turret mooring system, shipping it more than 2,000 nautical miles to Nantong, China.
PTSC Offshore Services (POS) has completed the fabrication, pre-commissioning and handover of the Block B turret mooring system, following an earlier turret built in Vietnam for the Lac Da Vang project, the company said.
From Lac Da Vang to Block B
In 2025, POS completed fabrication and pre-commissioning of a turret system for the Lac Da Vang field development project (Block 15-1/05, Cuu Long basin), operated by Murphy Oil. That project provided the experience for POS to carry out the 2026 Block B turret project for the Block B – O Mon gas project chain, operated by Phu Quoc POC.
Both turret systems were fabricated and pre-commissioned in Vietnam.
Role of the Turret Mooring System
The turret is a key part of the mooring system for an offshore floating storage and offloading (FSO) unit, allowing the vessel to rotate 360 degrees around the mooring point to adapt to wind, wave and current direction.
Pre-commissioning is the stage in which the completion status and readiness of the system within the scope of work are checked and confirmed before handover. Work on the Block B turret included integrating the lifting turret head into the chain table and turning tests on the turndown sheave assembly.
Sea Voyage to China
After completion at the POS workshop, the Block B turret was moved to PTSC Downstream Port and then shipped more than 2,000 nautical miles to Nantong Strongwind port in China, where it was handed over to the customer for connection to the FSO vessel.