PETRONAS Names PFLNG Tiga, World’s First Nearshore Floating LNG Facility, for Sabah
PETRONAS held the naming ceremony for PFLNG Tiga, a 2 mtpa nearshore FLNG facility built by JGC and Samsung Heavy Industries, due to start operations in Sabah in Q3 2027.
Petroliam Nasional Bhd (PETRONAS) is building PFLNG Tiga, the world’s first nearshore floating liquefied natural gas (FLNG) facility, which is expected to start operations at the Sipitang Oil and Gas Industrial Park in Sabah in the third quarter of 2027.
Quick Skim
Third FLNG Facility Extends PETRONAS Production Scope
PFLNG Tiga marks PETRONAS’ third FLNG installation following PFLNG Satu and PFLNG Dua. The development introduces nearshore production capability to PETRONAS’ existing portfolio, which includes shallow-water and deepwater FLNG operations.
Datuk Adif Zulkifli, PETRONAS executive vice-president and chief executive officer of gas and maritime business, said PETRONAS progressed from shallow-water LNG production with PFLNG Satu in 2016 to deepwater operations with PFLNG Dua, then to nearshore production with PFLNG Tiga.
“This journey is not defined by being first for its own sake. It is defined by our willingness to challenge conventional approaches, adapt our technology to different operating conditions and find practical ways to unlock gas resources,” he said.
Engineering and Construction by JGC Corporation and Samsung Heavy Industries
PFLNG Tiga is being built by a consortium of Japan’s JGC Corporation and South Korea’s Samsung Heavy Industries, which secured the engineering, procurement, construction and commissioning contract in December 2022. This facility represents the second collaboration between PETRONAS and the consortium following PFLNG Dua.
The official naming ceremony was held at the Samsung Heavy Industries Shipyard on Geoje Island, South Korea, on 24 November, attended by JGC Corporation president Shoji Yamada, Samsung Heavy Industries president Lee Wang-geun and Malaysian Ambassador to the Republic of Korea Datuk Mohd Zamruni Khalid.
Design, Capacity and Deployment Timeline
The FLNG facility measures 281 metres in length, 64 metres in width and 32 metres in depth. It has a production capacity of two million tonnes per annum, which will add to the combined capacity of 2.7 mtpa from PFLNG Satu and PFLNG Dua.
PFLNG Satu, the world’s first operational FLNG unit, was commissioned in 2016 with a capacity of 1.2 mtpa. It was initially deployed at the Kumang Cluster offshore Sarawak before being relocated to the Kebabangan cluster field offshore Sabah in 2019.
PFLNG Dua, which commenced production in February 2021 with a capacity of 1.5 mtpa, is the world’s first deepwater FLNG facility, operating at a water depth of up to 1,500 metres at the Block H Rotan gas field, 140 kilometres offshore Kota Kinabalu, Sabah.
PFLNG Tiga is targeted to sail away in mid-February 2027 and is expected to commence operations at the Sipitang Oil and Gas Industrial Park in the third quarter of 2027.
Adif said PFLNG Tiga would strengthen PETRONAS’ position as a global LNG supplier by improving its ability to serve customers across different markets and operating environments.