Hyundai Engineering Secures ₩2.3 Trillion in Power Plant Contracts for Yongin and Honam
Hyundai Engineering has won contracts worth about ₩2.3 trillion for a 1,050 MW CHP plant at SK Hynix’s Yongin cluster and a 500 MW LNG plant in Yeosu.
Hyundai Engineering has signed a ₩1.654 trillion contract to build a combined heat and power (CHP) plant supplying electricity and thermal energy to SK Hynix’s semiconductor cluster in Yongin, bringing its power plant contract wins over two months to about ₩2.3 trillion.
The company announced the contract on 25 November. Its client is Yongin CHP, a joint venture between Korea Midland Power and SK Innovation E&S, and work on the project has begun.
1,050 MW Yongin CHP Plant
The project involves building a 1,050 MW power generation facility and a 517 Gcal/h thermal energy production facility inside SK Hynix’s semiconductor industrial complex in Yongin, Gyeonggi Province. Hyundai Engineering will oversee engineering, procurement and construction (EPC), targeting completion in September 2030. The plant will meet the semiconductor complex’s demand for heat and steam.
A contract signing ceremony was held on 24 November, attended by Joo Woo-jung, CEO of Hyundai Engineering, Lee Young-jo, President of Korea Midland Power, and Lee Chung-gu, CEO of Yongin Combined Heat and Power Co., Ltd., among others.
500 MW Honam LNG Plant
Earlier, on 9 November, Hyundai Engineering signed a ₩630 billion contract with Korea East-West Power for the Honam Complex Power Plant Construction Project. The project involves constructing a 500 MW LNG complex power plant at the site of the former Honam Thermal Power Plant in Yeosu National Industrial Complex. Hyundai Engineering, as consortium leader, will handle design and procurement of major equipment, while POSCO E&C will manage construction. Groundbreaking is scheduled for June 2027, with completion targeted for May 2030.
Combined ₩2.284 Trillion in Contracts
Both projects were finalised under main contracts about two months after Hyundai Engineering was selected as preferred bidder in September. The combined contract value is ₩2.284 trillion.
“Having secured power plant business foundations in the capital and Honam regions, we plan to expand into next-generation energy sectors such as hydrogen power and SMRs (small modular reactors),” a Hyundai Engineering source said.
Source: The Chosun Ilbo
Photo: Hyundai Engineering/The Chosun Ilbo