Lambruk Mulwala Futures Proposes Staged 350 MW Data Centre Campus in Mulwala, NSW
Lambruk Mulwala Futures has proposed a three-stage data centre campus with a maximum grid demand of 350 MW in Mulwala, NSW, alongside a 27-hectare industrial precinct.
Australian developer Lambruk Mulwala Futures has proposed a staged data centre campus with a maximum grid demand of 350 MW in Mulwala, southern New South Wales, alongside a separate 27-hectare industrial precinct.
The project is at an early planning stage, with the developer yet to secure a major development partner and electricity supply currently indicated by Essential Energy for the first stage only, W.Media reported.
Site and staging
The campus would occupy approximately 62 hectares of a 168ha site on the northern edge of Mulwala, west of the railway line and between Tocumwal Road, Lambruck Lane and Savernake Road. The land is about 390 metres from Essential Energy’s Mulwala 132 kV zone substation and adjoins the existing Mulwala Solar Farm, which has approval for 80 MW of generation, of which approximately 31 MW has been built.
Lambruk proposes to build up to three data halls sequentially, with each stage dependent on the network being able to supply the additional demand. The developer estimates computing equipment would account for approximately 250–280 MW, with the remainder required for cooling and other equipment. Land is also set aside for a potential fourth hall, which would need additional network capacity and a separate planning approval.
Grid connection
The developer’s website says Essential Energy has advised that the local network has capacity for the first stage, with later stages depending on connection studies and any required network upgrades. No formal connection agreement or capacity allocation has been disclosed.
Planned electrical infrastructure includes a switching yard and substation linked to the zone substation through an easement, plus battery storage. Lambruk intends to use batteries and flexible computing loads to meet NSW Data Centre Guidelines requiring a 25% cut in grid demand for up to two hours during grid stress, without relying on diesel generation.
Planning pathway
The site is zoned RU1 Primary Production and R2 Low Density Residential, neither of which permits a data centre. Lambruk is seeking advice from the NSW Department of Planning, Housing and Infrastructure and intends to ask Federation Council to support a rezoning.
The project is proposed to proceed as State Significant Development. Lambruk is targeting a scoping report in December 2026 and an Environmental Impact Statement in March or April 2027, with public exhibition targeted for mid-2027.
Ownership and water
Lambruk Mulwala Futures is described as 100% Australian-owned and backed by local capital, with infrastructure advisory firm Lecroma managing development and community engagement. Job and investment estimates will be released once project studies are complete.
The closed-loop cooling system would use water from the landowner’s bore for the initial fill, and town water would not be used for cooling. Early engagement with Federation Council and neighbours began in late October, with a first public briefing planned for Mulwala in December.
Photo: The Border Mail