Intium Delivers Transmission Line for 243 MWp Maryvale Solar and Battery Project
Intium completed a nine-kilometre 132 kV transmission line in NSW, enabling grid connection for Gentari’s 243 MWp Maryvale solar and battery storage facility.
Sydney-based infrastructure company Intium has finished constructing a new 132 kV transmission line near Wellington in central western New South Wales, facilitating the grid connection for Gentari’s Maryvale solar and battery project.
Quick Skim
The nine-kilometre overhead transmission line links the Maryvale site to Essential Energy’s Geurie Zone substation. This connection point is critical for the project to export electricity to the NSW network. Intium completed the work on budget and about three months ahead of schedule.
Construction Delivered for Essential Energy’s Network
Intium managed the construction and commissioning programme on behalf of network operator Essential Energy. The project involved installing the 132 kV overhead line using steel and concrete poles, alongside a high-capacity fibre optic cable for communications.
The company stated that the transmission line is now complete and awaiting energisation. Intium noted the project demonstrates the potential of an end-to-end delivery model to address grid connection delays, which are often a bottleneck for renewable energy developments.
Maryvale Combines Large-Scale Solar and Battery Storage
The Maryvale project spans 360 hectares and integrates a 243 MWp solar photovoltaic installation with a 172 MW / 409 MWh battery energy storage system (BESS). It ranks among Australia’s largest sites using DC-coupled technology to optimise energy output and storage management.
Scheduled to commence commercial operations in mid-2027, the facility aims to support grid stability with enhanced system strength and inertia in an area of NSW with high renewable penetration.
DC-Coupled System Offers Efficiency and Flexibility
Gentari explained that by connecting the BESS directly to the DC side of the solar inverters, Maryvale can capture excess midday solar generation, reduce energy losses from AC-DC conversions, and optimise overall output without expanding its land footprint.
The battery storage system can firm and smooth variable solar generation, shift energy supply to better align with demand, and provide grid services such as Frequency Control Ancillary Services (FCAS), which help regulate grid frequency.
Project Secured through Government Energy Storage Agreement
Maryvale was among the first renewable projects in NSW to secure a Long Term Energy Storage Agreement (LTESA) through government auctions. This contract underpins its battery storage capacity and aligns with the state’s push to integrate more large-scale energy storage assets to support renewables.