Maritime and Port Authority of Singapore Marks Completion of Tuas Port Phase 2 Northern Berths Reclamation
MPA celebrates completion of reclamation for Tuas Port Phase 2 Northern Berths, advancing Singapore’s maritime infrastructure capacity and capabilities.
The Maritime and Port Authority of Singapore (MPA) announced the completion of the land reclamation works for the Northern Berths of Tuas Port Phase 2, a key step in expanding port capacity and reinforcing Singapore’s position as a global transshipment hub.
Quick Skim
Completion of Reclamation Marks Strategic Progress
MPA’s Chief Executive, Mr Ang Wee Keong, spoke at a ceremony recognising the reclamation milestone, known as the Finger 3 portion of the Tuas Port Phase 2 development. The closure follows the reclamation of Phase 1 completed in November 2021 and adds significant new land to the port’s infrastructure.
With reclamation works initialised in March 2018 on previously open sea, the newly formed land will support expansion of Singapore’s port capacity by providing new deep-water berths dedicated to container handling. The Northern Berths will complement the 14 berths currently operational in Phase 1.
Tuas Port’s Expanded Capacity and Technological Focus
Once fully developed across four phases in the 2040s, Tuas Port is planned to have a handling capacity of 65 million TEUs annually. Phase 2 alone will introduce 21 deep-water berths, substantially increasing throughput capability.
The development integrates automation, digitalisation and advanced technologies to support operational efficiency and resilience amid uncertainties affecting global trade and supply chains, according to MPA.
Engineering and Environmental Challenges Addressed
The reclamation project entailed intricate engineering activities including seawall construction, ground improvement and placing of large concrete caissons. Work required precise coordination to manage marine conditions, tides and traffic while allowing phased handover to PSA, the port operator.
Environmental considerations formed a key aspect of the approach, with coral relocation initiatives around Sultan Shoal and the use of biodegradable vertical drains to improve ground conditions. MPA highlighted these actions as indicative of the balance sought between engineering requirements and ecological sustainability.
Project Execution Amid Operational Challenges
The Northern Berths reclamation involved in excess of 24 million man-hours contributed by over 197 companies. The workforce comprised engineers, contractors, marine crews and other specialists.
Operations were affected by pandemic-related disruptions such as manpower shortages and supply chain issues. Nevertheless, project teams demonstrated adaptability to maintain progress with safety protocols in place.